Romsey, Kettlewells Road - Road Construction

Road upgrades on Kettlewells Road in Romsey have now been completed from from the Melbourne-Lancefield Road intersection to 108 Kettlewells Road. 

The project included the following:

  • 1.4km of existing unsealed road was upgraded and sealed from Melbourne-Lancefield Road to 108 Kettlewells Road.
  • roadside drainage improvements.

Works began in late November 2023 and were completed on 28 February 2024.

An upgraded bus shelter at intersection of Melbourne-Lancefield Road is also set to be completed by mid-March.

These works are funded by the Victorian Government and the Gravel Pit Operations Reserve.

Location

Kettlewells Road, Romsey 3434  View Map

Google Map