New Gisborne, Sauer Road - Road Reconstruction

Road works were completed between Ladd Road and Payne Road on Sauer Road, New Gisborne.

The project included:

  • full pavement reconstruction from Ladd Road to Payne Road
  • new 1.5 wide concrete footpath from Ladd Road to Payne Road
  • pram crossings at intersections
  • underground drainage installation and road side drainage improvements.

These works were funded by the 2022/23 Capital Works Program.

The works commenced in mid-April and were completed by mid September 2023.